Project Start Date: 2017-06-17th Project Expected End Date: 2017-06-18th Budget Allocated: 5,645,000.00 Budget Used so far: 1,741,832.80 Project Status: Incomplete
Project Start Date: 2017-03-1st Project Expected End Date: 2017-06-17th Budget Allocated: 26,000,000.00 Budget Used so far: 8,948,106.60 Project Status: Incomplete
Project Start Date: 2017-09-1st Project Expected End Date: – Budget Allocated: 6,000,000.00 Budget Used so far: 0 Project Status: Incomplete
Proposed Construction of Revenue Shades for Revenue Collectors and 10 Solar Panels for Ward Offices
Project Start Date: 2017-07-17th Project Expected End Date: 2017-06-18th Budget Allocated: 5,000,000.00 Budget Used so far: 1,867,218.36 Project Status: Incomplete
Project Start Date: Procurement stage Project Expected End Date: – Budget Allocated: 5,000,000.00 Budget Used so far: – Project Status: Incomplete
Project Start Date: Procurement stage Project Expected End Date: – Budget Allocated: 6,000,000.00 Budget Used so far: – Project Status: Incomplete
Project Start Date: Procurement stage Project Expected End Date: – Budget Allocated: 22,000,000.00 Budget Used so far: – Project Status: Incomplete
Project Start Date: 2015-03-30th Project Expected End Date: – Budget Allocated: 57,838,351.22 Budget Used so far: 23,135,340.42 Project Status: Incomplete